Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·
Plate № 05 · 2023 · Case Study

Mulholland Addition

Mulholland, LA

Cantilevered hillside wing with a primary suite reading room and view deck.

Type
Attached Addition
Size
1,150 sq ft
Cost
$520K
Permit-to-CofO
14 mo
Plate № 05Mulholland Addition, Mulholland, LA

01 — Brief

The brief.

Cantilevered hillside wing with a primary suite reading room and view deck.

The owner came to the studio with a 1,150 sq ft program and a hard cost ceiling. We responded with a fixed-fee feasibility document inside one business day, then locked the contract at $520K and delivered the Certificate of Occupancy in 14 mo.

Architecture, structural and Title 24 engineering, plan check management, and construction were all handled in-house under a single P&L — no coordination tax, no finger-pointing on corrections.

02 — Cost

Where the $520K went.

Allocation derived from the contract budget and reconciled against the studio's published methodology — see the full cost breakdown for category-by-category methodology.

  • Soft costs

    $62K
    Share12%

    Design, structural + Title 24 engineering, plan check and city fees.

  • Site & utilities

    $73K
    Share14%

    Excavation, foundation, sewer/water taps, sub-panel and trenching.

  • Hard construction

    $343K
    Share66%

    Framing, envelope, MEP rough-in, finishes, fixtures and appliances.

  • Contingency held

    $42K
    Share8%

    Reserved for unforeseen conditions; unspent balance returned at close.

03 — Timeline

14 mo, four phases.

The breakdown below tracks the actual permit-to-CofO calendar. Read more about the studio's standard schedule on the process page.

  1. Phase 01

    Feasibility & design

    15 wk

    Site survey, schematic design, structural concept, fixed-fee proposal.

  2. Phase 02

    Plan check & permit

    15 wk

    LADBS plan check, corrections cycle, school + utility fee clearance.

  3. Phase 03

    Construction

    24 wk

    Foundation, framing, envelope, MEP rough-in, finishes and fixtures.

  4. Phase 04

    Inspections & CofO

    6 wk

    Final inspections, punch list, owner orientation, Certificate of Occupancy.

04 — Neighborhood

Mulholland, LA.

Mulholland, LA sets the constraints for this build — setbacks, mature-tree protection, and the rhythm of the surrounding street frontages all shape the massing. The attached addition reads as quiet from the curb and generous inside, which is the brief we hold to on every addition we deliver in the area.

See the city desk for Mulholland

05 — Field notes

What we'd repeat — and what we'd revisit.

First-hand notes from the project lead, recorded at closeout. Published as part of our standing commitment to ship lessons, not just photos.

  1. Repeat

    Pre-stage the panel upgrade

    LADWP-coordinated sub-panel work was scheduled before framing closed, which kept rough-in inspection on the original calendar. We'd protect the same buffer on every detached build at this 1,150 sq ft program.

  2. Revisit

    Front-load Title 24 review

    Energy compliance corrections added late in plan check stretched the calendar. On the next addition of comparable size, we'll lock the Title 24 envelope before the first plan-check submittal rather than during corrections.

  3. Owner brief

    Allow one design review per phase

    Owners who held a single, prepared review per phase — feasibility, plan check, construction, closeout — kept the schedule and budget inside the contract. The reverse pattern (frequent informal changes) is the most common cost driver we see.