Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·

ADUs in Beverly Hills

Tight lot coverage, strict design review, and high-value rents. ADUs here pencil quickly when zoning allows.

Permit authority
City of Beverly Hills Community Developmenta
Plan check days
120–180a

Modeled

Median lot
7,200 sq ftb

Modeled

1-BR rent
$3,400/moc

Market data

Starting from
$165Kd

Firm

Cost / sq ft
$525–$650d

Firm

2-BR rent
$4,800/moc

Market data

Est. annual ROI
9–12%e

Modeled

Figures are typical ranges for the Beverly Hills market — not a quote. See methodology & sources below for how each number is derived.

§ I · Pricing

What an ADU costs in Beverly Hills.

  • ≈ 400 sq ft

    Garage conversion

    from $165K

  • 480 sq ft

    Detached studio

    from $285K

  • 750 sq ft

    Detached 1-BR

    from $365K

  • 1,000 sq ft

    Detached 2-BR

    from $445K

    Premium finish standard

Pricing spread$165K$445K
§ II · Permits

The path through City of Beverly.

LADWP service upgrades common on pre-1970 panels — budget 8–12 wks.

Plan check window
120–180 days
Permit + impact fees
$28K–$42K
Authority
City of Beverly Hills Community Development
Standard plans
Custom plans typical
§ III · Timeline

From contract to certificate of occupancy.

  1. 01

    Feasibility & survey

    APN pull, zoning, overlays, utility records.

    1–3 wks
  2. 02

    Design & Title 24

    Schematic, structural, energy compliance.

    4–8 wks
  3. 03

    Permitting

    Plan check at the local jurisdiction.

    see above
  4. 04

    Foundation & framing

    Mobilize, pour, frame, dry-in.

    8–12 wks
  5. 05

    MEP & finishes

    Rough-in, drywall, kitchen, bath, paint.

    10–14 wks
  6. 06

    Inspections & closeout

    Final inspections, certificate of occupancy.

    2–3 wks
Phase duration33 weeks · 7.5 months
  • Feasibility & survey1–3 wks
  • Design & Title 244–8 wks
  • Foundation & framing8–12 wks
  • MEP & finishes10–14 wks
  • Inspections & closeout2–3 wks

§ IV · Local notes

  • 01R-1 lots with rear-yard access are the easiest path.
  • 02Architectural review applies to street-visible elevations.
  • 03Hillside overlay adds geotech requirements above Sunset.
§ V · Featured projects
  • 06
    Plate № 062024

    Beverly Grove Cottage

    Detached ADU · 850 sq ft

    Local · Beverly Hills

  • 05
    Plate № 052023

    Mulholland Addition

    Attached Addition · 1,150 sq ft

    Local · Beverly Hills

  • 07
    Plate № 072025

    Culver Conversion

    Garage Conversion · 480 sq ft

    Adjacent submarket

All plates →
§ VI · Methodology & sources

How these Beverly Hills numbers are derived.

Every figure on this page falls into one of three confidence tiers. We publish the method so you can pressure-test the math before signing.

Firm
Pulled from our last 24 months of executed contracts in the region. Quoted ranges, not single points.
Market data
Sourced from third-party market trackers (Zillow, Apartments.com, RentCafe) within the last 90 days.
Modeled
Estimated from public records, jurisdictional bulletins, and our pro-forma model. Treat as a planning band.
  1. a

    Permit authority & plan check days

    City of Beverly Hills Community Development is the issuing jurisdiction. Plan-check window of 120–180 days reflects our last twelve submittals here for code-compliant ADU sets; complex sites (hillside, historic, coastal) trend longer. Verified against the jurisdiction's published service-level targets where available.

  2. b

    Median lot size

    Modeled from LA County Assessor parcel records (APN database) for R-1 and R-2 zoned residential parcels in the Beverly Hills city limits. Excludes commercial, multi-family ≥4 units, and parcels under 2,500 sq ft. Median, not mean — large estate lots do not skew the figure.

  3. c

    1-BR & 2-BR rents

    90-day trailing median asking rent for ADU-equivalent units (detached cottages, in-law suites, garage conversions) within the Beverly Hills ZIP codes, blended across Zillow Rent Index, Apartments.com, and RentCafe. Excludes furnished short-term listings.

  4. d

    Starting price & cost / sq ft

    Firm. Averaged from our last 24 months of signed contracts for comparable scope (Beverly Hills or adjacent submarket). Includes design, permits, construction, and standard finish package; excludes site-specific utility upgrades (see permit notes) and owner-furnished appliances. Quoted from $165K.

  5. e

    Estimated annual ROI

    Modeled as (annual gross rent − operating expenses) ÷ all-in project cost. Assumes 95% occupancy, 8% opex (insurance, maintenance, vacancy reserve), and the 2-BR rent above. Does not include appreciation, tax benefits, or financing leverage — those typically add 3–6 points. Published range of 9–12% reflects floor and ceiling scenarios.

Numbers refresh quarterly. For a binding figure on your specific parcel, request a feasibility letter — we'll pull live permit history, utility records, and comps within 48 hours.

VII

§ VII · Beverly Hills · 7 entries

Questions, answered for Beverly Hills.

The answers below use Beverly Hills's own permit window, fees, and rents — not generic county-wide ranges. For the full reference, see the Reference Desk.

Don't see your question? The full Reference Desk has every answer across cost, permits, SB-9, rentals, and process.

§ VI · Begin a project

Start your Beverly Hills ADU.

Free 30-minute feasibility call. We'll review your parcel and reply within one business day.

Project cityBeverly Hills
Or use the full contact form →

Other cities