Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·Vol. I ·California ADU Desk ·Licensed · Bonded · Insured ·CSLB #1098432 ·BBB A+ Accredited ·120+ ADUs Delivered ·Starting $250K ·10–16% ROI ·Los Angeles ·Bay Area ·
Plate № 09 · 2025 · Case Study

Manhattan Beach Studio

Manhattan Beach

Beach-facing studio with cedar interior and an outdoor shower garden.

Type
Detached ADU
Size
550 sq ft
Cost
$245K
Permit-to-CofO
9 mo
Plate № 09Manhattan Beach Studio, Manhattan Beach

01 — Brief

The brief.

Beach-facing studio with cedar interior and an outdoor shower garden.

The owner came to the studio with a 550 sq ft program and a hard cost ceiling. We responded with a fixed-fee feasibility document inside one business day, then locked the contract at $245K and delivered the Certificate of Occupancy in 9 mo.

Architecture, structural and Title 24 engineering, plan check management, and construction were all handled in-house under a single P&L — no coordination tax, no finger-pointing on corrections.

02 — Cost

Where the $245K went.

Allocation derived from the contract budget and reconciled against the studio's published methodology — see the full cost breakdown for category-by-category methodology.

  • Soft costs

    $29K
    Share12%

    Design, structural + Title 24 engineering, plan check and city fees.

  • Site & utilities

    $34K
    Share14%

    Excavation, foundation, sewer/water taps, sub-panel and trenching.

  • Hard construction

    $162K
    Share66%

    Framing, envelope, MEP rough-in, finishes, fixtures and appliances.

  • Contingency held

    $20K
    Share8%

    Reserved for unforeseen conditions; unspent balance returned at close.

03 — Timeline

9 mo, four phases.

The breakdown below tracks the actual permit-to-CofO calendar. Read more about the studio's standard schedule on the process page.

  1. Phase 01

    Feasibility & design

    10 wk

    Site survey, schematic design, structural concept, fixed-fee proposal.

  2. Phase 02

    Plan check & permit

    10 wk

    LADBS plan check, corrections cycle, school + utility fee clearance.

  3. Phase 03

    Construction

    16 wk

    Foundation, framing, envelope, MEP rough-in, finishes and fixtures.

  4. Phase 04

    Inspections & CofO

    4 wk

    Final inspections, punch list, owner orientation, Certificate of Occupancy.

04 — Neighborhood

Manhattan Beach.

Manhattan Beach sets the constraints for this build — setbacks, mature-tree protection, and the rhythm of the surrounding street frontages all shape the massing. The detached adu reads as quiet from the curb and generous inside, which is the brief we hold to on every detached we deliver in the area.

See the city desk for Manhattan Beach

05 — Field notes

What we'd repeat — and what we'd revisit.

First-hand notes from the project lead, recorded at closeout. Published as part of our standing commitment to ship lessons, not just photos.

  1. Repeat

    Pre-stage the panel upgrade

    LADWP-coordinated sub-panel work was scheduled before framing closed, which kept rough-in inspection on the original calendar. We'd protect the same buffer on every detached build at this 550 sq ft program.

  2. Revisit

    Order long-lead finishes earlier

    Two finish materials arrived inside the punch-list window, which compressed final inspections. We're now placing finish POs at the start of construction on builds of this scope.

  3. Owner brief

    Allow one design review per phase

    Owners who held a single, prepared review per phase — feasibility, plan check, construction, closeout — kept the schedule and budget inside the contract. The reverse pattern (frequent informal changes) is the most common cost driver we see.